Type
Archive
Project number
1050
Council Districts
02, 03, 04

Scope

Includes signal upgrades, fiber communications, and signal timing optimization from Marietta St to North Ave.

Paid

Project Start

Design Finish

Feb 2018

Construction Start

May 2017

Construction Finish

Jul 2019
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Planning/Scoping
Planning/Scoping
Engineering/Design
Engineering/Design
Procurement
Procurement
Construction
Construction
Closeout
Closeout