Bus Shelters & Bus Rider Experience Improvements

Sidewalks

Type

Sidewalks

Project Number

4095

Council Districts

Citywide

Scope

Installation of Bus Shelters and other amenities at identified “high-need” stop locations along MARTA bus routes.

Current Budget

$3,400,000.00

Paid

$0.00
Project Start
2025-01-28

Anticipated Design Finish

2027-02-26

Construction Start

2026-03-26
Construction Finish
2028-06-20

Disclaimer: Project schedules and scopes are subject to change.