Safe Streets

Barge Rd Sidewalk Installation

Sidewalks

Type

Sidewalks

Project Number

4086

Council Districts

11

Scope

Sidewalk installations to address missing segments along the corridor as identified by ATLDOT’s Safety, Equity, and Mobility analysis.

Current Budget

$1,473,571.00

Paid

$0.00
Project Start
2024-04-10

Anticipated Design Finish

2028-01-20

Construction Start

2026-05-29
Construction Finish
2026-08-26

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.