McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW McLendon Avenue NE from Candler Street NE to Sterling Street NE Moores Mill Road NE & Ridgewood Road NW

Safe Streets

ADA Improvements – Local Neighborhoods

Archive

Type

Archive

Project Number

1027

Council Districts

02, 05

Scope

Includes resurfacing, curbing, and ADA ramps on 3rd Ave from Alston Dr to Memorial Dr. Also includes ADA ramp installation and sidewalk repair in the Midtown, Candler Park, Poncey Highland, and Old Fourth Ward neighborhoods, and along North Avenue and Hurt St at Freedom Park.

Current Budget

$1,471,271.49

Paid

$1471271.49
Project Start
2016-11-30
Anticipated Design Finish
2019-10-26

Construction Start

2019-09-02
Construction Finish
2020-10-23

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.