Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

2024 LMIG Street Resurfacing

Street Repairs

Type

Street Repairs

Project Number

3065

Council Districts

All

Scope

Asphalt street resurfacing, with installation, upgrade and repair of ADA-compliant ramps; utility adjustments; and pavement markings and striping within the City of Atlanta.

Current Budget

$14,902,352.72

Paid

$10270847.20
Project Start
2024-01-08

Anticipated Design Finish

Construction Start

2025-06-19
Construction Finish
2026-02-13

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout