2019 LMIG Resurfacing

Archive

Type

Archive

Project Number

3042

Council Districts

All

Scope

Asphalt street resurfacing, milling, and point repairs; roadway striping, ADA-compliant ramp upgrades and installation; drainage, utility and other miscellaneous structure adjustments; and concrete work in the ROW at various locations throughout the City.

Current Budget

$6,124,688.10

Paid

$6124689.10
Project Start

Anticipated Design Finish

Construction Start

2021-09-13
Construction Finish
2021-12-31