Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE Colmer Avenue SE from Moreland Avenue SE to Mortimer Street SE North Avenue NE from Oakdale Road NE to Candler Park Drive NE Tuxedo Road NW from Northside Drive NW to West Paces Ferry Road NW FIFA Fan Festival Road Closures and Delivery

Safe Streets

15th St Extension

Roadway Improvements

Type

Roadway Improvements

Project Number

1072

Council Districts

02, 03

Scope

Includes the extension of 15th St two blocks westward from West Peachtree St to Williams St to improve traffic circulation for vehicles, bicycles, and pedestrians through the Midtown area.

Current Budget

$6,815,581.56

Paid

$5833649.89
Project Start
2016-11-02

Anticipated Design Finish

2022-01-28

Construction Start

2024-02-26
Construction Finish
2026-05-29

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.

Scroll to Top