Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW

Safe Streets

15th St Extension

Roadway Improvements

Type

Roadway Improvements

Project Number

1072

Council Districts

02, 03

Scope

Includes the extension of 15th St two blocks westward from West Peachtree St to Williams St to improve traffic circulation for vehicles, bicycles, and pedestrians through the Midtown area.

Current Budget

$6,815,581.56

Paid

$5833649.89
Project Start
2016-11-02

Anticipated Design Finish

2022-01-28

Construction Start

2024-02-26
Construction Finish
2026-05-29

Disclaimer: Project schedules and scopes are subject to change.