Safe Streets

14th St Sidewalk Installation

Sidewalks

Type

Sidewalks

Project Number

4080

Council Districts

3

Scope

Sidewalk installations to address missing segments along the corridor as identified by ATLDOT’s Safety, Equity, and Mobility analysis.

Current Budget

$107,066.00

Paid

$13265.33
Project Start
2024-04-11

Anticipated Design Finish

2026-10-12

Construction Start

2027-01-11
Construction Finish
2027-04-10

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout