Noble Drive NE from Johnson Road NE to Meadowvale Avenue NE Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Baker St NE/NW

Archive

Type

Archive

Project Number

5012

Council Districts

1 & 4

Scope

AURA Bond-World Cup Prep Resurfacing, Group 01 – Piedmont Ave NE to Marietta St.

Current Budget

$1,730,043.34

Paid

$912637.20
Project Start
2024-08-26

Anticipated Design Finish

2024-12-06

Construction Start

2025-06-03
Construction Finish
2025-08-28

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout