Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Resurfacing Flamingo Drive SW

Street Repairs

Type

Street Repairs

Project Number

4142

Council Districts

10

Scope

This project consists of resurfacing of 1.19 centerline miles on Flamingo Drive SW. Also included in the scope is restriping, resetting of manholes and water valves belonging to the COA up to grade with a concrete pad.

Current Budget

$1,091,065.00

Paid

$0.00
Project Start
2025-09-25

Anticipated Design Finish

NA

Construction Start

2026-02-12
Construction Finish
2026-07-23

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.

Scroll to Top