Safe Streets

Marietta Boulevard Bridge Deck Repair

Bridges

Type

Bridges

Project Number

4068

Council Districts

3

Scope

Repair failed section of bridge deck with through hole and exposed rebars in span 1, right lane of the north bound traffic. Repair or rebuild failed joints in spans 1 and 2 and rebuild joint headers. Remove loose and spalled concrete in this area, form new rebars and tie to existing where feasible and pour new concrete to form a new bridge deck. Repair spalled concrete areas with exposed reinforcement in span 1 and approaches.

Current Budget

$753,707.00

Paid

$99000.00
Project Start
2023-11-10

Anticipated Design Finish

NA

Construction Start

2025-02-20
Construction Finish
2026-07-31

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout