Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Marietta Blvd Safe Street

Safe Streets

Type

Safe Streets

Project Number

4018

Council Districts

3,9

Scope

Local match for planned federalized rebuild of the Marietta Blvd Corridor and safety improvements wherever possible.

Current Budget

$4,300,000.00

Paid

$4130.49
Project Start
2023-09-11

Anticipated Design Finish

2027-07-04

Construction Start

2027-12-02
Construction Finish
2029-02-28

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.