Safe Streets

Fairburn Rd Sidewalk Installation

Sidewalks

Type

Sidewalks

Project Number

4022

Council Districts

10,11

Scope

Addressing missing sidewalk segments on Fairburn Road from Hogan Rd SW to Alexandria Dr SW and from Kenner Dr SW to Thompson Dr NW (note the sidewalk from Kenner Dr SW to MLK Jr is covered by the Renew Fairburn Rd Improvements project# 1006)

Current Budget

$2,358,394.00

Paid

$0.00
Project Start
2024-02-28

Anticipated Design Finish

NA

Construction Start

2026-03-26
Construction Finish
2026-11-06

Disclaimer: Project schedules and scopes are subject to change.