Safe Streets

Atlanta Traffic Control Center (ATCC)

Signals

Type

Signals

Project Number

3012

Council Districts

04,10

Scope

Includes installation of Intelligent Transportation System (ITS) non-intrusive detection at three (5) intersections within the City of Atlanta.

Current Budget

$700,970.00

Paid

$156206.96
Project Start
2020-01-28

Anticipated Design Finish

2026-05-01

Construction Start

2026-12-03
Construction Finish
2027-11-02

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout