Safe Streets

Unpaved Roadways – Phase I Group 1

Roadway Improvements

Type

Roadway Improvements

Project Number

1082

Council Districts

01, 03, 05, 06, 09

Scope

Includes paving of unpaved portions of Braeburn Rd, Main St, and Hirsch St.

Current Budget

$2,703,447.87

Paid

$2225046.83
Project Start
2016-03-18

Anticipated Design Finish

2019-12-06

Construction Start

2024-02-23
Construction Finish
2025-12-01

Disclaimer: Project schedules and scopes are subject to change.