Noble Drive NE from Johnson Road NE to Meadowvale Avenue NE Ford Street NW from Spring Avenue NW to the Dead End Howell Mill Road from Trabert Avenue NW to Huff Road NW 10th Street NE from Piedmont Avenue NE to Monroe Drive NE Techwood Drive NW from North Avenue NW to Bobby Dodd Way NW Woodland Avenue SE from Lyndale Drive SE to Burn Street SE

Safe Streets

Piedmont Ave Complete Street

Safe Streets

Type

Safe Streets

Project Number

1015

Council Districts

02, 06

Scope

Includes road resurfacing, sidewalk and curb improvements, a protected bicycle lane, and landscaping from Ponce De Leon Ave to 15th St.

Current Budget

$5,000,000.00

Paid

$752291.46
Project Start
2017-08-31

Anticipated Design Finish

2021-08-31

Construction Start

2025-06-18
Construction Finish
2027-03-09

Disclaimer: Project schedules and scopes are subject to change.

Phase

  • Not Started
  • Planning/Scoping
  • Engineering/Design
  • Procurement
  • Construction
  • Closeout

No related events selected.

Scroll to Top