Boulevard Pedestrian Improvements

Type
Project number
1098
Council Districts
02, 05

Scope

Includes installing curb bulb outs and optimizing right-of-way along Boulevard between Highland Ave and Boulevard Pl. Project also includes construction of mid-block crosswalks, flashing beacons, pedestrian refuge islands, a short sidewalk widening, ADA ramps, and other pedestrian mobility and safety improvements at signalized intersections.

Paid

Project Start

Jun 2018

Design Finish

Construction Start

Aug 2025

Construction Finish

Aug 2026
Disclaimer: Project schedules and scopes are subject to change.