Type
Safe Streets
Project number
1096
Council Districts
01

Scope

CONCEPT STUDY ONLY. Concept study to evaluate improvement alternatives to provide protected bicycle lanes and improved pedestrian facilities along South Boulevard from Woodward Ave to McDonough Blvd.

Paid

Project Start

Sep 2019

Design Finish

Aug 2024

Construction Start

Jan 2025

Construction Finish

Dec 2025
Disclaimer: Project schedules and scopes are subject to change.

Percent Complete

Phase

Not Started
Not Started
Preconstruction
Planning & Development
Procurement
Design
Construction
Construction
Complete
Complete